Since 1966, the Montréal métro has been at the very heart of city life. With its 68 stations, the network oversees more than 1.2 million passenger rides every day. Many people are focused and committed to maintain the network and ensure that customers find it inviting and reliable. Beyond the work being carried out every day, the STM is continually undertaking renovation and construction work to keep the network strong.
Here are the network projects that are currently underway. To learn more about the nature of the work being done and alternative travel options, click on the station name.
| Berri-UQAM |
May 6 to June
22
|
May 6 to June 1
DESCRIPTION OF
WORK
Dismantling of a decorative column on the mezzanine level and on the Orange and Green lines.
From 9 p.m. to closing:
The right-hand side of the staircase is closed leading from the mezzanine towards Honoré-Beaugrand, Côte-Vertu, and Longueuil-Université-de-Sherbrooke.
At all times between April 29 and May 25.
One of the three escalators leading from Côte-Vertu to the Honoré-Beaugrand platform is closed.
For more information |
ALTERNATIVE ROUTE
You can use the left-hand side of the staircase and the adjoining escalators.
|
May 27 to June 22 from 9 p.m. to closing
DESCRIPTION OF
WORK
Dismantling of a decorative column on the mezzanine level.
The left-hand side of the staircase leading to Côte-Vertu and Longueuil-Université-de-Sherbrooke from the mezzanine level is closed.
For more information |
ALTERNATIVE ROUTE
You can use the right-hand side of the staircase.
|
June 11 to 29
DESCRIPTION OF
WORK
Entrance leading to Gare d’autocars de Montréal (bus terminal) and to the terminus stop for the 747 airport shuttle will be closed.
For more information |
ALTERNATIVE ROUTE
You can use either Berri or St.Catherine entrances. To reach the bus terminal, walk about 350 metres heading north.
|
| Guy-Concordia |
March 5 to August 26
|
DESCRIPTION OF
WORK
Major renovations - Complete closing of Saint-Mathieu entrance.
For more information |
ALTERNATIVE ROUTE
The Guy métro station entrance can be used.
|
| McGill |
March 2012 to
March 2013
|
Until March 2013
DESCRIPTION OF
WORK
It will involve the replacement of travertine tiles adorning the station walls.
Partial closing of the entrance located at: 2055, University Street. The entrance doors on President-Kennedy Street will be boarded up.
For more information |
ALTERNATIVE ROUTE
The entrance on President-Kennedy will be closed to customers. However, the University entrance can be used.
|
May 7 to 28
From 7 p.m. until closing, Sunday to Wednesday, and from 10 p.m. until closing on Thursday and Friday
DESCRIPTION OF
WORK
The turnstiles on the Eaton Centre side, facing the Carlton Cards store, will be locked.
For more information |
ALTERNATIVE ROUTE
You can use the turnstiles next to the fare control booth at all times. |
June 4 to 29
DESCRIPTION OF
WORK
The right-hand side of the staircase between the Angrignon platform at the front of the train and the upper mezzanine is closed.
For more information |
ALTERNATIVE ROUTE
You can still use the left-hand side of the staircase.
|
June 26 to July 20
DESCRIPTION OF
WORK
The middle section of the Angrignon platform will be partially blocked off by a partition wall along with two sets of seats.
For more information |
ALTERNATIVE ROUTE
You can still use the full length of the platform.
|
| Plamondon |
From January to October
|
DESCRIPTION OF
WORK
Water drainage work around the vaulted ceiling area.
For more information |
ALTERNATIVE ROUTE
Traffic flow is not affected.
|
| Snowdon |
April 30 to the end of May
|
DESCRIPTION OF
WORK
Raising of the platform heading towards Montmorency facing the first four front car doors. |
ALTERNATIVE ROUTE
Traffic flow is not affected.
|
| Square-Victoria |
From March to December
|
DESCRIPTION OF
WORK
Water drainage work around the vaulted ceiling area.
For more information |
ALTERNATIVE ROUTE
Traffic flow is not affected
|
| Université-de-Montréal |
April 30 to the end of May
|
April 30 to the end of May
DESCRIPTION OF
WORK
Rebuilding of staircase
Closing of right-hand side of the staircase.
Which staircase?
Far end of the métro platform
Heading towards Snowdon
The staircase leading to the fare collector booth level will be closed.
|
ALTERNATIVE ROUTE
The left-hand side of the staircase can be used.
|
April 30 to the end of May
DESCRIPTION OF
WORK
Rebuilding of staircase
Closing of left-hand side of the staircase.
Which staircase?
Front end of the platform
Heading towards St-Michel
The staircase leading to the fare collector booth level will be closed.
|
ALTERNATIVE ROUTE
The right-hand side of the staircase can be used.
|
May 1 to the end of May
DESCRIPTION OF
WORK
Rebuilding of staircase
Closing of the left-hand side of the staircase.
Which staircase?
From the Édouard-Montpetit entrance
Staircase leading to the fare collector booth level will be closed.
|
ALTERNATIVE ROUTE
The right-hand side of the staircase can be used.
|
| Fleury mechanical ventilation station |
November 2011 to fall 2013
|
Location of ventilation station
The new structure will be built between the following civic addresses 10 353 and 10 383 on Berri Street (between Sauvé and Henri-Bourassa métro stations).
| News Update |
Fresh air supply for workers
It is possible that you may perceive a distinctive sound coming from the job site. This noise will be coming from the ventilation system. This allows the air to be cooled inside the well. This ventilation system will be running all summer long.
In order to meet the initial project deadline, it will be necessary for work to continue on Saturdays, and on certain weekday evenings until the end of May.
We have now reached the excavation stage.
The digging of the main part of the station’s well structure has been completed. The excavation of the subterranean gallery’s horizontal section connecting the well to the métro tunnel is now underway.
|
For more information
|
| Hermine mechanical ventilation station |
Fall 2012
to summer 2014
|
New mechanical ventilation station construction project
As part of its program for refurbishing métro infrastructure, we are building a new mechanical ventilation station on the Orange line, between Square-Victoria and Place-d’Armes métro stations.
For more information
|
|